GreenBuddies

BESS Logistics: A key phase that determines success

BESS Logistics: A key phase that determines success

Batteries

29.10.2025

Transporting and installing battery energy storage systems (BESS) is one of the most complex stages of an EPC workflow. Unlike standard PV builds—where the heaviest logistics challenge is often the substation—BESS introduces new risks: extreme weight, oversize loads, hazardous-materials classification (ADR in Europe), and near-zero tolerance for planning errors. All of this directly affects project IRR; delays or mishandling during BESS delivery can materially erode returns.

BESS transport is not ordinary haulage

Utility-scale battery containers are most often shipped in 20-foot enclosures, with gross weights up to ~45 tons. Such consignments are both overweight and hazardous (lithium cells fall under dangerous goods rules, e.g., ADR). Transport therefore requires a specialist carrier with the right equipment, permits, and experience.

BESS demands an experienced team and rigorous planning

Logistics for utility-scale BESS requires deep expertise and meticulous preparation. Early engagement of logistics partners, geotechs, designers, and local authorities is the best insurance for a smooth delivery. Errors at this stage cause schedule slips and significant cost overruns. Treat this phase as mission-critical.

Permits and lead times

BESS logistics should be planned at least a month in advance. The carrier must obtain special permits for oversize and hazardous loads. If lifting/unloading occurs from a public roadway, additional permissions—lane occupation or full closure—are typically required. That can add months, involving local authorities, road operators, and other stakeholders. Any oversight risks schedule slippage and cost escalation.

Terrain and access routes are decisive

Battery containers and cranes require a stable, load-bearing platform. A temporary gravel track typical for PV sites is rarely sufficient. Access roads and laydown/crane pads must carry a truck with a 45-ton container and a heavy crane plus counterweight trucks. A geotechnical survey is essential; road and pad build-ups should be engineered and constructed accordingly.

Logistics coordination down to the last detail

Early alignment with the logistics provider is critical. They will define technical constraints: turn radii, crane outrigger requirements, route passability, bridge clearance limits, etc. Based on these inputs, the designer specifies exact handling zones, required ground bearing capacity, and the approved route to the installation point.

On-site handling: Precision with zero compromise

A BESS container is placed as a single, heavy assembly and must be set with high positional accuracy. A few centimeters off can trigger time-consuming rehandling. The foundation must be prepared precisely—typically a reinforced concrete slab with pre-formed penetrations for bottom-entry cabling. A single 2 MW / 4.5 MWh container can require 30–35 power cables across DC, AC, and data, so conduit layout and pull lengths must be finalized in advance.

Blog

Blog

Every month in the Newsletter we bring you tips and interesting facts about photovoltaics and charging infrastructure in general. You will find out news about our projects, collaborations, as well as the internal life of Greenbuddies.

Subscribe to our newsletter

This site is protected by reCAPTCHA and the GooglePrivacy Policy and Terms of Service apply.
GreenBuddies
Shining since
4 500 000 000 B.C.
Phone
+420 736 644 444
Email
Office address
Greenbuddies, s.r.o.
Mendíků 1396/9
140 00 Prague 4
Czech Republic
Greenbuddies Group