The Greenbuddies team carried out mechanical and electrical work on a ground-mounted agrivoltaic power plant in Sweden. The scope of work included the assembly of the support structure, the installation of photovoltaic modules and inverters, and complete DC cabling, including connections to the inverters. The project also included AC cabling, such as the installation of cable glands, the laying of data cables, and the grounding of the photovoltaic system.
Greenbuddies also provided comprehensive site and project management, reviewed the project documentation, and accepted the materials delivered to the construction site. All work was carried out in accordance with applicable local and European regulations regarding workplace safety, construction, and electrical installations. The scope of supply also included the necessary hand tools, transportation, and accommodations for the installation teams.