Inverters: 30
PV Modules: 11 840
DC Cables: 60 km
GreenBuddies

Inverters: 30
PV Modules: 11 840
DC Cables: 60 km
Complete EPC delivery of mechanical and electrical installation of ground-mounted photovoltaic power plant, driving 4,645 piles. Commissioning and connection to the grid.
The Greenbuddies team oversaw the comprehensive implementation of a ground-mounted photovoltaic power station under an EPC contract. The scope of the project included the preparation of design documentation for construction, the supply of photovoltaic modules, inverters and mounting structures, the complete mechanical installation, the driving of piles and the installation of the photovoltaic system. The project also included DC and AC electrical installation work, data cabling, transformer connection, earthing and associated construction work.
Greenbuddies also provided comprehensive site and project management, surveying work, the necessary machinery, site facilities, fencing, waste management and the coordination of the individual phases of construction. The scope of supply also included the verification of documentation, the acceptance of materials on site, the commissioning of equipment and ensuring that the project complied with local and European regulations.