The project was commissioned by one of our long-term partners in the development and construction of photovoltaic power plants, SENS
![Schwaighausen, DE - 6 MWp Freefield](/_next/image?url=https%3A%2F%2Fgreenbuddies.s3.eu-central-1.amazonaws.com%2F1_XL_8a5564b365.jpeg&w=3840&q=75)
Schwaighausen
Germany
Freefields
Alternative Energy Sources
Photovoltaics
Sustainability
9.4 MWp
Client
Schedule
Contract signature: June 2022
Start of work: June 2022
Cempletion of DC connection: October 2022
Complete mechanical installation including hammering of 7,700 posts and complete wiring.