Inverters: 21
PV Modules: 9 700
DC Cables: 80 km
GreenBuddies
Inverters: 21
PV Modules: 9 700
DC Cables: 80 km
Complete EPC delivery of mechanical and electrical installation of ground-mounted PV system with battery. Commissioning and connection to the grid, including delivery of all certificates.
The Greenbuddies team successfully completed the construction of a 6.9 MWp ground-mounted photovoltaic power plant.