Mecklar

Germany
Roof projects
9.5 MWp

Client

The client was Dr Metje Consulting, which implements photovoltaic solutions across Europe and has worked with Greenbuddies on a number of projects.

Schedule

Contract signature: October 2022

Start of work: November 2022

Completion of DC connection: April 2023

The Greenbuddies team carried out the installation and electrical work on the rooftop photovoltaic power station. The scope of work included the installation of the support structure, including the ballast system, the fitting of photovoltaic modules and DC inverters, and the laying of all DC cabling, including connections to the inverters and subsequent DC tests. The project also involved coordinating individual activities on site and ensuring the smooth progress of the installation work.
Greenbuddies also ensured the review of the design and technical documentation, the receipt of materials on site, and compliance with all project requirements. All work was carried out in accordance with the relevant local and European regulations governing health and safety, construction, and electrical installations. The project also included the provision of the necessary hand tools, transport for workers, and accommodation for the implementation teams.

GreenBuddies
Shining since
4 500 000 000 B.C.
Phone
+420 736 644 444
Email
Office address
Greenbuddies, s.r.o.
Mendíků 1396/9
140 00 Prague 4
Czech Republic
Greenbuddies Group