GreenBuddies

Mappach

Germany
Freefields
12.6 MWp

Client

The project was commissioned by one of our long-standing partners for the development and construction of photovoltaic power plants, SENS.

Schedule

Contract signature: November 2022

Start of work: December 2022

Completion of DC connection: April 2023

The Greenbuddies team carried out all the construction, mechanical and electrical installation work on the ground-mounted photovoltaic power station. The scope of work included the preparation and execution of individual construction tasks, the assembly of the support structure, and the installation of photovoltaic modules and associated technical components. The project also included comprehensive electrical installation work for both direct and alternating current, including the laying of cabling, the wiring of individual components and ensuring the correct functioning of the entire system.
Greenbuddies also coordinated the individual phases of construction, organised work on site and monitored the execution of individual tasks in accordance with the project documentation and the client’s requirements. All work was carried out in accordance with the relevant local and European regulations relating to health and safety, construction and electrical installations. The scope of supply also included the provision of the necessary tools and technical equipment, as well as the coordination of the implementation team.

Mappach freefield PV from a bird's perspective
GreenBuddies
Shining since
4 500 000 000 B.C.
Phone
+420 736 644 444
Email
Office address
Greenbuddies, s.r.o.
Mendíků 1396/9
140 00 Prague 4
Czech Republic
Greenbuddies Group