Inverters: 99
PV Modules: 61 776
DC cables: 400 km
GreenBuddies
Inverters: 99
PV Modules: 61 776
DC cables: 400 km
Installation of mounting system, photovoltaic modules and electrical installation of DC cables and inverters.
Greenbuddies handled the installation of the mechanical and electrical components of the photovoltaic power plant. The scope of work included assembling the support structure, installing photovoltaic modules and inverters, inspecting and tightening fasteners, laying DC cabling—including connections to the inverters—cable labeling, grounding, and structural bonding. The project also included DC and grounding tests, provision of machinery, construction site facilities, waste management, monitoring of work progress, construction supervision, and project management. Greenbuddies also ensured the review of documentation, acceptance of materials, and compliance with all local and European regulations.