GreenBuddies

Falköping

Sweden
Freefields
13.2 MWp

Components

Inverters: 31

PV Modules: 18 600

DC Cables: 80 km

Delivery

Installation of mounting system, photovoltaic modules, and electrical installation of DC cabling. Driving of 7,600 piles.

The Greenbuddies team handled the comprehensive execution of mechanical and electrical work on a ground-mounted photovoltaic power plant. The scope of work included driving a total of 7,600 piles using the necessary machinery, complete assembly of the support structure, and the subsequent installation of 18,600 photovoltaic modules with a capacity of 710 Wp and 31 inverters with a capacity of 330 kVA. The project also included DC cabling, including connections to the inverters, DC grounding, and waste management. Greenbuddies also provided comprehensive site and project management and coordinated the individual phases of construction.

The scope of work further included reviewing the design and technical documentation, accepting materials at the construction site, and ensuring that the implementation complied with project requirements. During construction, relevant local and European regulations regarding occupational safety, construction, and electrical installations were adhered to. The scope of supply also included the necessary hand tools, transportation of workers and machinery, and arrangements for the accommodation of the construction teams.

GreenBuddies
Shining since
4 500 000 000 B.C.
Phone
+420 736 644 444
Email
Office address
Greenbuddies, s.r.o.
Mendíků 1396/9
140 00 Prague 4
Czech Republic
Greenbuddies Group