Inverters: 1
PV Modules: 6 160
DC cables: 50 km
GreenBuddies

Inverters: 1
PV Modules: 6 160
DC cables: 50 km
Installation of the mounting system, photovoltaic modules, and electrical wiring for AC cables and inverters. Driving 2,640 piles.
The Greenbuddies team handled the comprehensive execution of mechanical, electrical, and construction work on a ground-mounted photovoltaic power plant. The scope included surveying work, pre-drilling 2,640 holes and subsequent pile driving, assembly of the support structure, and installation of photovoltaic modules and DC boxes. The project also included DC and high-voltage cabling, excavation work, laying of data cables, grounding, and connection of a weather station.
Greenbuddies also provided the foundations for the technical stations, 1,750 meters of perimeter fencing for the site (including gates), the necessary machinery, construction site facilities, waste management, and comprehensive site and project management. The work also included cold commissioning, documentation review, and material acceptance at the construction site. The project was carried out in accordance with applicable local and European regulations.