Benningen

Germany
Freefields
9.5 MWp

Client

The project was commissioned by one of our long-standing partners for the development and construction of photovoltaic power plants, SENS.

Schedule

Contract signature: March 2023

Start of work: March 2023

Completion of DC connection: February 2024

The Greenbuddies team carried out the construction, mechanical and related installation works on a ground-mounted photovoltaic power station to the extent specified in the project documentation and the client’s brief. The project involved providing all the necessary machinery for work on the construction site, including material-handling and earth-moving equipment. Greenbuddies also arranged for the supply of selected auxiliary installation materials, in particular materials for cable routes, earthing, AC cable terminations and other components required for the proper execution of the works.


The supply also included the review of project and technical documentation, the acceptance of materials on site, the internal coordination of individual activities and the provision of the necessary hand tools. All work was carried out in accordance with site regulations and the relevant local and European regulations governing health and safety, construction and electrical installations. Greenbuddies also arranged transport for workers, machinery and accommodation for the implementation teams.

GreenBuddies
Shining since
4 500 000 000 B.C.
Phone
+420 736 644 444
Email
Office address
Greenbuddies, s.r.o.
Mendíků 1396/9
140 00 Prague 4
Czech Republic
Greenbuddies Group