The project was commissioned by one of our long-standing partners for the development and construction of photovoltaic power plants, SENS.
Benningen
Germany
Alternative Energy Sources
Freefields
Photovoltaics
9.5 MWp
Client
Schedule
Contract signature: March 2023
Start of work: March 2023
Completion of DC connection: February 2024
Complete mechanical installation of the substructure and photovoltaic modules, including DC and AC wiring.