The project was commissioned by Solkompaniet, with whom Greenbuddies has been working on a number of projects.
Bålsta
9 MWp
Client
Components
Mounting system: Esdec FlatFix Wave East/West
Inverters: Sungrow 110 kW
PV modules: JA535
Schedule
Contract signature: May 2022
Start of work: June 2022
Completion of DC connection: December 2022
The flat roof of the 65,000 m2 Dagab food logistics centre in Bålsta is designed entirely according to the "PV rooftop ready" rules. Thanks to an ideally designed roof and choice of components, we built almost 9 MW in a record 3 months.
The main reasons for the fast construction and thus the early commissioning are: the material was lifted onto the roof by helicopter and evenly distributed on the roof as close to the installation site as possible, while the JA Solar 535 Wp jumbo panels with a size of 2285×1135 mm were used and placed on the Esdec mounting system.