The project was commissioned by one of Europe's leading solar companies, Svea Solar, with whom Greenbuddies has worked on a number of projects across Europe.

Agerum
Client
Components
Mounting system: PG group
Inverters: Solis 275 kW, Sineng 250 kW
PV modules: 655 Wp
Schedule
Contract signature: March 2023
Start of work: April 2023
Completion of DC connection: October 2023
The Greenbuddies team carried out the comprehensive mechanical and electrical works for a ground-mounted photovoltaic power station. The scope of work included driving piles, the complete assembly of the support structure, and the installation of photovoltaic modules and inverters. The project also included work relating to the transformer substation, complete DC cabling – including connections to the inverters and the performance of DC tests – the interconnection of individual technical components, and the laying of low-voltage AC cabling, including subsequent AC tests.
Greenbuddies also carried out checks on the design and technical documentation, took charge of material handover at the construction site, and coordinated the various assembly and electrical installation activities. All work was carried out in accordance with site regulations and the relevant local and European regulations governing health and safety, construction and electrical installations. The project also included the provision of the necessary hand tools, transport for workers and accommodation for the implementation teams.